June 19 – Committee receives Burnside’s Feasibility Study for bridge over the Beaver River.

June 20  – Installed first Map posts. Three new on Lower Loop. Maps to be installed once finalized.

June 21 – Lower grass trails cut with walk-behind mower.

June 22 – Grass trails on Upper Loop cut with walk behind mower in a thunder storm. Three additional map posts installed

June 29 – Trail Crew brushed out BVSC black snowshoe single track trail, brushed out about 50% of new single track in mid level.

July 4 – Meeting with Municipality of Grey Highlands to discuss bridge Feasibility Study.

July 8 – Review alternative proposed parking location on Grey Road 30.

July 12 – Install more Map Posts.

July 13 – Complete brushing out old mid-level single track trail. Flag and start brushing single track bypass on mid-level trail.

July 27 – Committee members to staff a booth at Flesherton Farmer’s Market.